State of Maine says Workday has shown 'no accountability' for farcical $56.4m HR upgrade

(2021/04/14)


Maine has accused Workday of showing "no accountability" for its part in a flawed process to replace the US state's HR system.

Following a [1]request for an official review into the $54.6m project , the Office of Program Evaluation and Government Accountability has published correspondence that Workday would almost certainly rather remain private.

[2]

In a [3]May 2020 letter to the SaaS vendor about the replacement of the state's ageing HR and finance system, Kirsten Figueroa, commissioner of the Maine Department of Administrative and Financial Services, said the project last year missed two go-live dates.

State of Maine orders review of $54.6m Workday project as it alleges delivery failure and threatens cancellation [4]READ MORE

[5]

Evaluation by the project management office discovered "significant gaps in configuration and testing, as well as best practices and methodology that had not been followed," she said.

The office also found that "project timeline contained inappropriate overlapping phases; exit criteria for various testing phases were not met; training and communication were inadequate; knowledge transfer to the State of Maine staff who will be supporting the product was extremely limited."

In the letter, Figueroa said: "There is a shared responsibility for these issues for both the Workday and State of Maine project staff. However, the Workday project staff have shown no accountability for their part in this flawed process…

"Reports to the Executive Steering Committee throughout the project were rosy and optimistic. At no point was the [committee] given any indication of the depth and the magnitude of the problems."

Figueroa went on to express doubt Workday could rectify problems with the project and frustration at the proposal that the state should be charged several million dollars more than agreed to get a usable system.

In a letter dated 25 February, Figueroa [6]wrote to Workday giving it notice that should it fail to remediate issues with the system within 30 days, the state would proceed with immediate termination of its professional services agreement with Workday.

Multiple legacy systems

The history of the project does, however, point to the possibility that problems may not only lie with the vendor.

In 2016, the state signed up ERP vendor Infor to provide the HR system and the pair [7]planned to have the system up and running in 2018 . That contract was "terminated for lack of delivery" in June 2018.

Later in 2018, Maine contracted Workday to provide an HR system, this time expecting a go-live date of 2020. That date has now been revised to 2022.

Maine currently uses multiple legacy systems which led to integration problems, inherently inefficient processes, and incompatibility with systems that are no longer supported.

In a [8]March 2021 letter to the Joint Standing Committees on Appropriations and Financial Affairs, Figueroa wrote that "significantly out-of-date computer systems" also required knowledge of computer languages that are no longer taught. She added that the problems had led to "considerable administrative burden and/or cost for the upkeep and functionality of these legacy systems" as well as "vulnerability to cyber-attack and/or malfunction."

Workday has been contacted for its response to the state's allegations.

Earlier Workday told The Register it was "committed to partnering with the State of Maine to successfully complete this project."

[9]

A spokeswoman went on to explain that "technology deployments are highly collaborative and require all parties, including customers, to participate and deliver on their commitments, and we have been doing our part to try and engage with the State to move the deployment forward. The State of Maine has no basis to terminate our agreement for cause." ®

Get our [10]Tech Resources



[1] https://www.theregister.com/2021/03/31/maine_workday_dispute/

[2] https://pubads.g.doubleclick.net/gampad/jump?co=1&iu=/6978/reg_offprem/saas&sz=300x50%7C300x100%7C300x250%7C300x251%7C300x252%7C300x600%7C300x601&tile=2&c=2YHcRnL57YY5Hlg-TXJCIJgAAAAU&t=ct%3Dns%26unitnum%3D2%26raptor%3Dcondor%26pos%3Dtop%26test%3D0

[3] http://legislature.maine.gov/doc/6509

[4] https://www.theregister.com/2021/03/31/maine_workday_dispute/

[5] https://pubads.g.doubleclick.net/gampad/jump?co=1&iu=/6978/reg_offprem/saas&sz=300x50%7C300x100%7C300x250%7C300x251%7C300x252%7C300x600%7C300x601&tile=3&c=33YHcRnL57YY5Hlg-TXJCIJgAAAAU&t=ct%3Dns%26unitnum%3D3%26raptor%3Deagle%26pos%3Dmid%26test%3D0

[6] https://legislature.maine.gov/doc/6265

[7] https://www.theregister.com/2021/03/31/maine_workday_dispute/

[8] https://legislature.maine.gov/doc/6263

[9] https://pubads.g.doubleclick.net/gampad/jump?co=1&iu=/6978/reg_offprem/saas&sz=300x50%7C300x100%7C300x250%7C300x251%7C300x252%7C300x600%7C300x601&tile=4&c=44YHcRnL57YY5Hlg-TXJCIJgAAAAU&t=ct%3Dns%26unitnum%3D4%26raptor%3Dfalcon%26pos%3Dmid%26test%3D0

[10] https://whitepapers.theregister.com/

Workday Project Manager

Steve K

I'd be surprised if Workday's Project Manager had not at least raised some of these concerns internally at least - would be interesting to see the Risks/Issues register!

It is possible that they were overruled of course on commercial grounds, or maybe overall Project Management was not actually in their scope.

Given the (published) issues with the previous Infor project, Scope/Requirements control should have been top of Workday's Risk assessment when taking on this project?

On the Maine side, surely the same level of introspection should have been performed - unless they were just relying on Workday to make it all magically happen?

Government Project...

IGotOut

Behind schedule and over cost.

Contact me when this isn't the case.

Who actually "owned" the programme / project plan as a deliverable?

Aristotles slow and dimwitted horse

Commercially, deliverables and the responsibility for the ownership and delivery of them are usually detailed out in the work contract between the two parties.

The overarching Programme and Project plan is then usually pulled together by the "owner" of the overall plan, from the leads from different workstreams such as Development, Data migration, Testing, Release, Business change etc etc. It is then their responsibility, sometimes with the assistance from a PMO or project support team to pull all of this together into a whole and then validate that (A) it works as an end to end plan, and (B) do all of the disparate teams and stakeholders agree to, and support it.

So who "owned" the plan?

Either way though, the PMs from both sides should have been regularly reviewing the plan and raising risks and issues etc if they felt it didn't work.

Potemkine!

Is there any IT multi-million project who gets on schedule, with all functionalities provided and with over cost?

jake

"Is there any IT multi-million project who gets on schedule, with all functionalities provided and with over cost?"

Most of them. I suspect you meant "without over cost", though.

Beer? It's 5 o'clock somewhere ...

Accountability

HildyJ

These days, the idea of accountability seems as quaint as punch cards.

Re: Accountability

jake

We live in a "QUICK! Find someone else to blame!" world, alas.

fidodogbreath

The office also found that "project timeline contained inappropriate overlapping phases; exit criteria for various testing phases were not met; training and communication were inadequate; knowledge transfer to [...] staff who will be supporting the product was extremely limited."

In other words, a successful consulting project. From the consultant's perspective, anyway.

jake

Not really. As a consultant, my job is to get in, do the job well, and get out again ... and hopefully never hear from the client ever again. Failures to communicate (as this undoubtedly is) do nothing but cause ongoing ulcers for all concerned. Intelligent people don't want that.

Now ask me why I don't work for governments, doctors, or lawyers anymore ...

It takes two to tango

Anonymous Coward

I gather it's quite lonely in the State of Maine.